Completed Projects
- EFİKAP3 İ.M.K.B. Schools / Aşkale
- Construction of 90 Permanent Earthquake Residences
- Erzurum Disaster Residences
- Ağrı 150 Bed State Hospital
- EFİKAP3 İ.M.K.B Schools / Ilıca
- İzmir Vakıflar Eşrefpaşa of Flats Construction
- EFİKAP3 İ.M.K.B. Schools / Karayazı
- EFİKAP3 İ.M.K.B. Schools / Kopal
- EFİKAP3 İ.M.K.B. Schools / Van
EFİKAP3 İ.M.K.B Schools Aşkale
Employer : Milli Eğitim Bakanlığı Yatırım Tesisler Daire Başkanlığı
Start Date : 07.09.2007
Finish Date : 13.04.2009
Work Information :
5 500 m2 Total Construction Area
High school with 16 classrooms
Landscaping and Infrastructure Construction
Place : Aşkale / Erzurum / Türkiye
Construction of 90 Permanent Earthquake Residence
Employer : Bayındırlık ve İskan Bakanlığı Yapı İşleri Genel Müdürlüğü
Start Date : 07.08.2003
Finish Date : 26.12.2003
Work Information :
13 500m2Total Construction Area
Residence of 90 earthquake
Landscaping and Infrastructure
Place : Bingöl / Türkiye
Erzurum Disaster Residence
Employer : Bayındırlık ve İskan Bakanlığı Yapı İşleri Genel Müdürlüğü
Start Date : 11.07.2004
Bitiş Tarihi : 13.10.2004
Finish Date :
Work Information :
6 000m2Total Construction Area
Residence of 38 Earthquake
Landscaping and Infastructure
Place : Karayazı / Erzurum / Türkiye
Ağrı 150 Bed State Hospital
Employer : Ağrı Bayındırlık ve İskan Müdürlüğü
Start Date : 11.01.2000
Finish Date : 31.12.2004
Work Information :
13 000m2 Total Construction Area
150 Bed State Hospital
Landscaping and Infrastructure
Place : Ağrı / Türkiye
EFİKAP3 İ.M.K.B. Schools / Ilıca
Employer : Milli Eğitim Bakanlığı Yatırım Tesisler Daire Başkanlığı
Start Date : 07.09.2007
Finish Date : 13.04.2009
Work Information :
11 000m2 Total Construction Area
High School with 24 classrooms
480-person dining hall
480-person female-male guesthouse
Place : Ilıca / Erzurum / Türkiye
İzmir Vakıflar Eşrefpaşa of Flats Construction
Employer : Vakıflar Genel Müdürlüğü İzmir Bölge Müdürlüğü
Start Date : 23.07.2008
Finish Date : 26.06.2009
Work Information :
3 450m2 Total Construction Area
20 Unit Apartment
Construction of 3 businesses
Place : İzmir / Türkiye
EFİKAP3 İ.M.K.B. Schools / Karayazı
Employer : Milli Eğitim Bakanlığı Yatırım Tesisler Daire Başkanlığı
Start Date : 07.09.2007
Finish Date: 13.04.2009
Work Information :
6 300m2 Total Construction Area
High School with 24 classrooms
Construction of a kindergarten
Construction of dining hall for 500 people
Place : Karayazı / Erzurum / Türkiye
EFİKAP3 İ.M.K.B Schools / Kopal
Employer : Milli Eğitim Bakanlığı Yatırım Tesisler Daire Başkanlığı
Start Date : 07.09.2007
Finish Date : 13.04.2009
Work Information :
4 240m2 Total Construction Area
High School with 16 classrooms
Çevre Düzenleme and Infrastructure Construciton
Place : Karaçoban / Erzurum / Türkiye
EFİKAP3 İ.M.K.B. Schools / Van
Employer : Milli Eğitim Bakanlığı Yatırım Tesisler Daire Başkanlığı
Start Date : 07.09.2007
Finish Date : 13.04.2009
Work Information :
12 800m2 Toplam İnşaat Alanı
High School with 24 classrooms
480 Single Girl - Female Boarding
Gym
10 Lodgings
Place : Gürpınar / Van / Türkiye